31 December 2025

Design & Independent Check

Anticipated Programme:

Design and independent check – March – December 2025

Subject to Committee Approval and available funding:

Tender – January - February 2026

Award – April 2026

Construction – May 2026 – January 2027


11 March 2025

Marr Area Committee

24 January 2025

Options Report Survey Closes - 12pm

21 January 2025

Birse Community Drop-In

14 January 2025

Aboyne Community Drop_in

18 December 2024

December Update

11 October 2024

Aboyne Bridge Update

30 August 2024

Aboyne Bridge Update

12 July 2024

July Update

15 May 2024

Aboyne Bridge - May Update

08 April 2024

Monthly Update

20 March 2024

Survey Data published

28 February 2024

Online Engagement Closes

21 February 2024

Community Drop-in Event - Online Engagement Live